Presolicitation: Shipyard Infrastructure Optimization Program Multi-Mission Dry Dock, Multiple Award Construction Contract

Wednesday, June 17, 2026

CNO) breifing

Navy Signals $30 Billion Dry Dock Program for Bremerton Shipyard

 

The U.S. Navy has announced plans for a massive new contracting program supporting construction of the Multi-Mission Dry Dock at Puget Sound Naval Shipyard, a project that could generate billions in economic activity and create contracting opportunities throughout Kitsap County and the broader Pacific Northwest over the next decade.

The planned $30 billion contract vehicle is among the largest federal construction programs ever associated with the Bremerton shipyard and represents a major milestone in the Navy's long-term modernization strategy. While the prime contracts will likely be awarded to large national construction firms, local businesses across construction, engineering, logistics, manufacturing, and professional services should closely monitor the project as significant subcontracting opportunities emerge.

The investment reinforces the strategic importance of Naval Base Kitsap and Puget Sound Naval Shipyard, which already serve as key economic drivers for the region. As planning advances, KEDA will continue working with partners to help Kitsap businesses understand and prepare for opportunities tied to this transformative federal investment. 

  • Contract ceiling: $30 billion
  • Duration: Up to 10 yearsAnticipated award: May 2027
  • Approximately five prime contractors expected to be selected.
  • Largest Shipyard Infrastructure Project in Generations
Chief of Naval Operations Adm. Daryl Caudle and Master Chief Petty Officer of the Navy John J. Perryman visited Puget Sound Naval Shipyard & Intermediate Maintenance Facility, June 

The project is a cornerstone of the Navy's Shipyard Infrastructure Optimization Program (SIOP) and will create a new dry dock capable of servicing:

  • Ford-class aircraft carriers
  • Nimitz-class aircraft carriers
  • Other surface and submarine vessels

The dry dock will replace aging infrastructure and ensure Puget Sound Naval Shipyard remains a critical maintenance hub for decades.

Massive Construction Opportunity

Individual task orders are expected to range from:

$2 billion to $6 billion

Major work packages include:

 

Marine Package ($2–3 billion)

  • Demolition
  • Dredging
  • Cofferdam construction
  • Ground improvements

Dry Dock Package ($3.5–4.5 billion)

  • Dry dock construction
  • Excavation
  • Pressure relief systems
  • Pump installations

Infrastructure Package ($3.5–4.5 billion)

  • Electrical substations
  • Utility tunnels
  • Support facilities
  • Crane rails
  • Permanent utilities

Caisson Package ($200–300 million)

Fabrication and installation of the dry dock gate system
Major Opportunity for Local Supply Chains

While only a handful of national firms will likely qualify as prime contractors due to the requirement for $2 billion in single-project bonding capacity, the scale of the project will create substantial opportunities for:

  • Construction subcontractors
  • Engineering firms
  • Environmental services
  • Marine construction companies
  • Equipment suppliers
  • Material providers
  • Transportation and logistics firms
  • Professional services businesses
  • What Happens Next

Key milestones include:

  1. Sources Sought: June 2026
  2. Industry Day: August 2026
  3. Solicitation Release: September 2026
  4. Prime Contract Awards: May 2027
  5. First major construction task order award: June 2028

See presolicatation notice on SAM.GOV

Category: SIOP, PSNS & IMF, NBK, BizFair